Services

AUGER CAST PILES
  CHEMICAL AND CEMENT GROUTING
  PREPLACED AGGREGATE CONCRETE
  RETENTION SYSTEMS
  SOIL AND ROCK ANCHORS
  DIAGONAL TIE-BACKS

Auger Cast Piles

Auger Cast Piles are installed by rotating a continuously flighted hollow shaft auger into the soil to a specified depth.  High strength cement grout is pumped under pressure through the hollow shaft as the auger is slowly withdrawn.  The resulting grout column hardens and forms an auger cast pile.  Reinforcing, when required, can be installed while the cement grout is still fluid or, in the case of full length single reinforcing bars, through the hollow shaft of the auger prior to the withdrawal and grouting process.  Auger Cast Piles can be used as friction piles, where the superstructure load is transferred to the soil through friction between the pile surface and the soil; as an end bearing pile, where the superstructure load is transferred  through the pile tip into a hard stratum of soil or rock; as an anchor pile, where hydrostatic or other uplift forces are resisted though a full length tendon embedded in the grout column; as a vertical component of a continuous auger cast curtain wall in temporary or permanent shoring systems and below grade walls; and as a temporary or permanent diagonal tie-back in auger cast curtain walls, beam and lagging walls, and sheet pile walls.

 

Advantages:

bullet

Less noise - Auger cast piles are a drilled and pumped pile not a driven pile; which eliminates the hammer impact noise created by driving piles

bullet

No objectionable vibration - The elimination of a pile driving hammer allows the installation of auger cast piles adjacent to existing structures without the danger of settlement or damage to existing footings, walls, other structural components, or existing nearby equipment.

bullet

No casing required - During the installation of an auger cast pile: the earth filled auger maintains the shape for the pile hole during the drilling phase, the pressures produced by the grout pump during the withdrawal and grouting phase exceed the lateral pressures exerted by the soil, and while the grout is still fluid, the lateral pressures per foot of depth from the grout exceed those pressures per foot of depth of the soil.

bullet

Can be installed in limited headroom conditions - Auger sections can be manufactured to accommodate installation of auger cast piles inside of existing buildings with as little as 7-10 feet of headroom.

bullet

Soil at each pile hole can be inspected -  The grout that is pumped into the pile displaces the existing soil for the entire length of the pile.  This displacing action makes the soil along the length available for visual inspection and testing.

 

TYPICAL AUGER CAST PILE LOADS FOR VARIOUS DIAMETERS
(actual pile capabilities are dependent upon soil conditions)

Nominal Size of Pile
(inches)

Loading Range
(tons)
Compression strength of mortar (pis)

12"

10-50 3000-4000
14" 50-75 3000-4000
16" 75-100 3500-4500
18" 100-150 4000-5000

The diameters indicated are the most common used for auger cast piles.  However, auger cast piles with diameters of 24", 30" and 36" have been successfully utilized with tests being conducted as high as 350 tons.  Pile design capabilities can be verified with several different testing procedures: ASTM D 1143 tests the compressive capacity of a pile by applying a static axial compressive load; ASTM D 4945 tests the compressive capacity of a pile by applying a dynamic axial high-strain impact load; ASTM D 3689 tests the tensile capacity of a pile by applying a static axial tensile load; ASTM D 3966 tests the lateral deflection of a pile by applying a static load perpendicular to the axis of the pile; and ASTM D 5882 test the integrity of the pile shaft by applying a dynamic axial low-strain impact load.

back to top

Chemical and Cement Grouting

Chemical Based Grouting
Soil stabilization by the introduction of  a chemical grout is achieved by combining a silicate base with a gel producing reactant and water and then pumping  the mixture under pressure through open ended pipes into the soil.  The resulting system can be designed to set in minutes by varying the amount of the reactant used.  Different additives can be introduced to achieve specific results but in general chemical based grout can achieve the following:

bullet

Increase the load bearing capacity of soil formations under existing walls, footings, and foundation pads for machinery.

bullet

Fortify granular soil formations under existing structures adjacent to new construction sites, eliminating the possibility of cave-ins and settlement of existing structures.

bullet

Control or eliminate water seepage due to hydrostatic pressures or the natural flow of ground water.  Permeability of sandy soil; can usually be reduced to less than that of unweathered clay.  Soil masses or rocks can become essential impermeable when completely saturated with chemical grout.

Chemical grout is non-toxic, eliminating the need for protective clothing during placement.  It stabilizes soil effectively and economically often eliminating the need for costly sheeting and shoring.  On congested job sites, where a large area would be required to install sheeting and shoring, the injection of a chemical based grout is a viable alternative.  Chemical based grout, when used in proper proportions, is immune to deterioration and demonstrates reasonable permanence by being dimensionally stable regardless of changes in temperature.  the ambient temperature however, is an important factor in the design oft he mix because of its effect on gel time.

Cement Based Grouting

Cement based grout is a combination of cement, pozolithihic filler, sand, water and fluidifier.  It is applied under pressure through existing floor slabs, walls, tunnel linings, and soil layers.  Filling voids that have developed below existing floor slabs or pavements is a primary use and in some cases, thought he use of a phased installation, slabs that have settled can be raised back to their original elevation.  compressive strengths reaching 8,000 psi can be achieved.  In most instances the cement based gout is mixed in site and fed directly to the pump. In cases where larger sized voids and crevices need to be filled, cement grout is pumped into a porous flexible bag ( a "Grout Bag") that is lowered into position where the void is to be filled.  Once the grout sets, the "Grout Bag" is held firmly in place against the surrounding walls sealing the voids.  This method of pressure grouting eliminates wash-away tendencies occasionally encountered during regular pressure grouting operations.  It is ideally suited for cutoff walls, diverting water flow and filling voids due to scour.  The "Grout Bag" Confinement Method is economical and stays where it is placed.


back to top

  Preplaced Aggregate Concrete

Preplaced Aggregate Concrete (PAC) was originally developed for structural repairs primarily because of its strength, excellent bonding ability to existing concrete, higher resistance to erosion and cavitations, minimal shrinkage, and uniform quality.  PAC lends itself to vertical and overhead types of construction such as: bridge piers and abutments, walls dams, tunnel linings, and spillways, etc.

In PAC work, clean coarse aggregate is placed in pre-positioned forms and a cement mortar is pumped into the aggregate mass from the bottom up, displacing air and/or water from spaces between the aggregate particles.  PAC can also be used in new construction as well as part of a structural repairs, the cement mortar penetrates the rough texture and surface of existing older concrete.  The practical elimination of setting and drying shrinkage provides a final monolithic concrete making the structure equal to or better than as originally built.  In new construction, as in the case of heavily reinforced concrete, the graded aggregate is rodded into place among the bars and the mortar is injected afterwards thus reducing the the risk of hidden voids that is inherent with the use of ordinary concrete.  Comprehensive strengths of PAC can reach as high as 7,000 psi.  It utilizes a greater proportion of coarse aggregate in its overall makeup.

back to top

Earth Retention Systems

When the difference between the working elevation of a site and the elevation of any existing structures, pavements, or utilities that need to be protected is substantial, and the site does not offer enough space to slope back the sides of the excavation, then an earth retention, shoring, or underpinning system is required.  The auger cast pile, when installed in a continuous auger cast cutoff wall, can be reinforced to resist lateral forces imposed by existing conditions.  The process by which a continuous auger cast cutoff wall is installed is twofold: First, a drilling a template is constructed.  The template is installed at eh lowest possible elevation, such as the top of existing footers or the top of existing sewers and utility lines.  Generally, the width and depth of the template is between 18 and 24 inches.  A reinforcing cage is installed the full length of the template and then tubes forms of the proper diameter are installed  through the ties of the cage. Following the pouring and curing of the template, the auger cast piles are installed through the forms and down to the required depth.  The piles can be reinforced with full length bars, reinforcing cages, or, in the case of heavy lateral loads, with full length wide flange beams if required.  The excavation can continue once the vertical components of the wall have been cured.  In the case of deeper excavations; diagonal tie-backs, as described below, can be installed through the auger cast wall to provide additional resistance to lateral forces.  In some instances, the completed auger cast cutoff can be incorporated into the final project as an exposed retaining wall or the actual basement walls by covering its face with a shotcrete or otherwise aesthetic concrete covering.
 

Auger cast cofferdam with reinforced ring beams for Equalization Tank at the Division Avenue WWTP in Cleveland, OH

Soil and Rock Anchors

When tensile or uplift forces are anticipated, such as hydrostatic pressures on submerged tanks and wind loads on the legs of a tower, a system to resist those tensile forces is required. Auger cast piles can be utilized to resist uplift in cohesive and granular materials.  The method of placement remains the same but when tensile forces are anticipated, a full length reinforcing bar is installed in the pile.  Depending on the depth of the pile, the full length bar can be installed through the hollow shaft of the auger or placed after the grouting process is complete.  When the underlying subsurface material is solid bedrock then uplift is resisted through the use of a rock anchor.  Rock anchors are generally smaller in diameter than an auger cast pile; the equipment used to install them and the method of installation is also substantially different.  In both cases the full length reinforcing bar must be large enough to withstand the anticipated load and transfer it into the anchor.

Diagonal Tie-Backs

Auger cast piles can be installed as Tie-backs through sheet pile walls, beam and lagging walls, and auger cast cutoff walls.  essentially, a diagonal tie- back is a tension pile placed on a batter and an auger cast pile rig can be modified to install tie-backs on any angle up to approximately 60º from vertical.  Tie-backs installed through the face of the wall extend back beyond the limit of the theoretical failure plane and into competent soil.  For design purposes, no value should be assigned to the soil located in the failure plane.  High strength tensile bars (usually 150 ksi thread bar) are installed through the hollow shaft of the auger and embedded in the gout of the tie-back.  Bars can vary from simple epoxy coated steel for temporary retaining systems or fully encapsulated bars for permanent retaining systems.  The degree of encapsulation varies with the amount of corrosion protection required for the individual job. Once the grout in the tie-back has achieved the required strength the steel bars are post-tensioned which places the soil immediately behind the wall in compression and reduces the tendency of the wall to move inward as the excavation proceeds.
There are several advantages to using a diagonal tie-back:

bullet

Allows the area being excavated to remain free of struts and braces that would otherwise be required to prevent the soil surrounding the excavation from caving in.

bullet

Can be placed under existing footings without damaging the building above from unnecessary vibration or the undermining of the footings.

bullet

Can be installed with or without casing depending on the individual requirements of the job.